Stage 3: Plan the Project
 
 
Activities

 

What it is How to Templates/
Examples
 
 
How to: Hold Project Kick-Off Meeting

Recommended actions and strategies
The table below describes actions you can take to conduct a Project Kickoff Meeting:

 

What to do

How to do it

1

Determine Stakeholders

Identify Stakeholders to include in the Project Kickoff Meeting

2

Schedule Project Kickoff Meeting

Determine when Stakeholders are available and schedule the meeting.

3

Prepare the Agenda and Meeting Materials

Several days prior to the meeting, prepare and distribute the agenda and the approved Project Charter.

4

Hold Project Kickoff Meeting

Gather in a quiet room of adequate size for the group. 

Introduce the Sponsor(s), Project Manager, and Stakeholders. 

Review the approved Project Charter and respond to questions to clarify and ensure understanding. Keep the conversation focused.

Explain next steps planned to generate the Work Plan and Control Plan that will comprise the project Planning Stage.

5

Project Kickoff Meeting Follow-up

Send meeting minutes to Stakeholders for a follow-up review. Invite additions/corrections. 

Hold brief follow-up sessions with any Stakeholders who were unable to attend the meeting.

 

 